Electric Power Supply, Land Survey and Acquisition, Strategic Environmental Assessment, Security, Transaction Advisory Services
These projects are being undertaken by the Government of Kenya as critical infrastructure needed to boost the viability of the LAPSSET Corridor and to provide investors with the confidence they need to develop the project components.
Electric Power Supply
- Construction of 220KV line from Rabai to Hindi in Lamu County completed.
- Construction of a 33KV line to Lamu Port completed while another 33KV line to Lamu town is still under construction.
- Lamu – Garissa – Isiolo – Lokichar 220kV transmission line is at the financial negotiation stage.
- The government has awarded concession to Amu Power Ltd to construct and operate a 1000MW coal power plant in Lamu.
Land Survey and Acquisition
- LCDA has undertaken the preliminary survey in the counties of Lamu, Garissa and Isiolo. The report of this exercise is pending to be received from NLC.
- LCDA is in the process of developing a comprehensive guideline for acquiring the Isiolo-Moyale and Lokichar-Nadapal sections of the corridor.
Strategic Environmental Assessment
- The Strategic Environmental Assessment (SEA) process is ongoing.
- Inception report already submitted to the Authority.